Country boundaries: Natural Earth · All project points approximate
Counts describe register entries. A campus may have several installations or phases. The evidence filter separates operating AI installations from proposed projects, mixed infrastructure and programmes.
02 / THE WEEK IN REVIEW
Power. Planning. Politics.
A concise briefing on the decisions behind the build-out.
Friday cutoff · 18:00 UK time
LATEST DEVELOPMENT · 26 November 2026 · OUTSIDE THE SAVED WEEKLY ISSUE
US overseas data-centre remarks and UK project updates
The US president’s 20 November remarks introduced a policy risk for projects with US developers or anchor tenants. Published evidence for the Atlas still comes from operators, planning authorities and official rules.
US overseas construction proposal
President Trump threatened penalties or a tax on US firms building data centres abroad. On 22 November, Treasury Secretary Scott Bessent gave no mechanism and Microsoft President Brad Smith distinguished frontier training from other cloud workloads. As of 26 November, this review found no published implementing text and no UK project change publicly attributed to the remarks.
A 19 November US Commerce Department rule imposes controls on certain advanced computing exports and remote compute supplied to companies in specified jurisdictions. Its published scope includes transactions at overseas facilities. It does not set a general overseas construction tax.
Drax’s 23 November update says tenant discussions continue. The first phase depends on planning, regulatory and network approvals, commercial agreements and final investment decisions.
Falkirk Council says the 13 November deadline passed without a decision. The applicant declined to agree an extension, so a non-determination appeal is possible. The council update does not report an appeal or a decision.
Week ending Friday 20 November 2026, 18:00 GMT8 sourced items
Environment
•
Campaign groups march in Edinburgh against proposed AI data centres
Friends of the Earth Scotland said more than 80 organisations backed a Royal Mile march calling for public consultation before Scottish AI data-centre approvals. Its claims about energy, climate and community impacts are campaign positions, not official impact assessments.
Larbert deadline passes without a planning decision
Falkirk Council said the determination date for Apatura's proposed 300MW AI data centre expired after the applicant declined a further extension, creating a right to appeal for non-determination. The council is still assessing the application and taking comments on additional environmental information; the scheme is not approved.
Greater Manchester adopts a regional data-centre and compute strategy
The Combined Authority adopted a framework through 2032 covering investment, local planning and infrastructure, with tests for economic and social value, grid capacity and the region's 2038 net-zero goal. The strategy informs future decisions but does not itself approve any data-centre project.
Two new campuses enter pre-application stages in Sussex and Bedfordshire
DCD reported a proposed 100MW, five-building liquid-cooled Meridian One campus at Hickstead and a four-building Pace DC scheme near Bedford linked to solar and battery infrastructure. Neither has planning permission: Meridian One has not yet submitted an application, while Pace DC was preparing consultation before submission.
MPs are nominated to scrutinise the data-centre National Policy Statement
The Commons Liaison Committee nominated a cross-committee panel to examine the draft planning statement that would guide ministerial decisions on nationally significant schemes in England and Wales. The membership and chair remain subject to approval by the House.
Government puts pledged AI Growth Zone investment at £28bn
In a written parliamentary answer, AI minister Kanishka Narayan said developers had pledged an aggregate £28bn across the five AI Growth Zones. The figure is based on delivery partners' estimates and represents pledged investment, not completed construction or verified expenditure.
Blyth substation reaches consent milestone for Cambois connection
National Grid's November project update says all phase-one consents are secured for the Blyth Substation extension serving the Cambois data-centre campus, with substation construction due to start in winter 2026/27. This is an enabling grid project; it is not a new approval or construction start for the data-centre buildings.
Iomart enters exclusive talks over a sale of its UK data-centre business
Iomart said it was in bilateral exclusive discussions that could lead to disposal of its 12-site UK data-centre portfolio, mainly to reduce debt and fund its services businesses. No sale has been completed; any transaction would require shareholder approval.
The Atlas tracks publicly identifiable UK AI installations, projects and related infrastructure. This register was reviewed on . Each project shows when its evidence was last verified. We prioritise operator announcements and planning records, and attribute reported delays or potential tenants to their sources.
What the status colours mean
Green: operating. Yellow: construction or approval, kept as separate filters. Orange: proposed, in discussions or delayed. Red: paused or withdrawn. Approval alone is not evidence that building work has started.
Location and capacity limits
Markers indicate an approximate site area or town. They are not parcel boundaries. Capacity figures describe different things—IT load, total power, full buildout or zone potential—so they are not added together. No claim of national completeness is made.
Coverage by UK nation and open leads
The review covers operator announcements, national and devolved planning documents, and public research systems. It includes all four UK nations and distinguishes sites, developments and programmes. Unavailable decisions and undisclosed technical or tenant details are recorded with their limits.
England · Government AI Growth Zones, operator disclosures and planning registers for named projects. Planning or government source
Scotland · Scottish planning casework, council material and operator evidence, including EIDF and the distinct Edinburgh HPC programme. Planning or government source
Wales · Welsh Government casework, councils and operator disclosures, including the CWL1 host and its planned Nebius installation. Planning or government source
Northern Ireland · Derry campus consent and sources for the mixed-use Kelvin2 research service. Planning or government source
Nscale Hayes · Operator lists an AI service in Hayes. The exact host and installation are unresolved.
BT / Nscale · Up to 14 MW is planned across three existing BT sites. The operator has not disclosed usable locations for individual markers.
Argyll / SambaNova · The service is evidenced in Scotland. The operator did not verify the physical host sufficiently to add a site marker.
AIRR heterogeneous system · The host competition remains open until 30 November. The published timetable targets notifying applicants by 8 January 2027. No host is verified.
Civo edge programme · The operator’s November update continues to identify Hertfordshire as its first project. Its exact site and commencement of live service remain unverified.
Amlwch Octel · The earlier AI conversion application and the later modular compound proposal are separate. The council register did not render during this review, so the latest decision remains unverified.
Coldstream planning status · The council record was inaccessible. The last verified evidence remains the earlier screening stage.
Culham is in Oxfordshire. A planning resolution, issued consent and discharge of conditions are separate milestones.
Era4’s Newport project is now The Mill. Consent for part of one building and wider campus plans are separate.
Teesworks campus permission and reports of Anthropic talks are distinct. No tenancy deal is assumed.
Stargate UK is a compute partnership; a chip-manufacturing hub was not verified. Its paused commitment does not mean existing Cobalt Park buildings are paused.
Scotland’s parliamentary call for a pause is separate from statutory planning directions. The verified requirement is an environmental impact assessment for new centres over 50MW.
Each issue covers the seven days ending Friday at 18:00 Europe/London, adjusting for BST and GMT. Items link to their original sources; opinion and campaign claims are attributed. Earlier issues remain available in the selector. Fewer items are used when there is less verified news.
DEFINITION / EVIDENCE / INCLUSION
What belongs in the AI category?
An AI data centre is designed and equipped primarily for large-scale AI computation, with specialised processors and the power distribution, cooling, structural capacity and networking needed to support them.
This is the Atlas’s working definition for assessing individual sites and installations.
Documentary scope assessment: 26 November 2026
Operating evidence and development stage
The register identifies 12 evidenced operating AI installations. This is a count of entries assessed here. The filters show which records describe a development, a shared host or a programme.
Primary AI purpose must be supported by specialised processors and engineering evidence. Capacity, investment, planning permission, an AI customer’s name or growth-zone designation alone is insufficient. An announced design is not an equipped operating installation. Published evidence is not an engineering certification; structural detail can remain undisclosed. Missing evidence is not proof that a project cannot support AI.
We assess the named installation or deployment. Separate records can share a host, as with the systems at Kao Harlow. Where public evidence is incomplete, each assessment states what remains unknown.
68 entries shown
Google Waltham CrossMixed / broader infrastructure · AI predominance unverifiedOperational · Project evidence 2026-11-26
Fit with the Atlas definition
Mixed / broader infrastructure · AI predominance unverified
Primary AI purpose
Google describes cloud, Search, Maps and growing AI demand.
Specialised processors
Site-specific processors and their deployment scale are not disclosed in the cited release.
Supporting engineering
Opening and general infrastructure are documented; predominant AI purpose is not established.
Operating mixed-service facility; not counted as evidenced AI operation.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
QTS Cambois campusMixed / broader infrastructure · AI predominance unverifiedUnder construction · Project evidence 2026-11-26
Fit with the Atlas definition
Mixed / broader infrastructure · AI predominance unverified
Primary AI purpose
Corgan describes both traditional and high-density deployments.
Specialised processors
No named AI installation or processors verified for this campus.
Supporting engineering
72MW IT buildings and closed-loop cooling support capability, not proof of primary AI use.
Outline consent, enabling works, first-phase construction and later build-out are separate. Early 2028 remains a first-phase target.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
AI proposal / commitment · technical evidence incomplete
Primary AI purpose
A CoreWeave customer commitment supports AI intent.
Specialised processors
Named AI cloud customer; a site-specific processor inventory is not verified here.
Supporting engineering
New building is under construction; recorded sources do not settle its complete AI engineering specification.
The separately proposed energy park and DV1 expansion are distinct projects. The summer 2027 completion date is a target.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
Kao Data KLON-03Documented AI design · live service unverifiedUnder construction · Project evidence 2026-11-26
Fit with the Atlas definition
Documented AI design · live service unverified
Primary AI purpose
Operator explicitly describes a purpose-built GPU AI / advanced-computing building.
Specialised processors
GPU-accelerated systems are specified as the intended deployment; no installed inventory confirmed.
Supporting engineering
Hybrid/direct-to-chip cooling and rack densities up to130kW are documented.
Documented AI design, not verified commissioning; separate from operational KLON-01/02.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
Nscale Loughton AI campusDocumented AI design · live service unverifiedDelayed · Project evidence 2026-11-26
Fit with the Atlas definition
Documented AI design · live service unverified
Primary AI purpose
Original primary announcement specifies an AI campus.
Specialised processors
23,040 NVIDIA GB300 GPUs in the original plan; not verified installed.
Supporting engineering
50MW AI/HPC plan, scalable power allocation and liquid-cooling design are documented.
Nscale says it is exploring alternative power. A replacement customer, power agreement and opening date remain unverified.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
AI proposal / commitment · technical evidence incomplete
Primary AI purpose
Developer describes AI-training purpose.
Specialised processors
No selected processor inventory verified.
Supporting engineering
Large proposed IT load and cooling intent; full AI system design not verified.
A conditional committee resolution is verified. An issued notice, start of works and the opening date remain unverified.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
Culham AI Growth ZoneProgramme / growth zone · not a facilityProposed · Project evidence 2026-11-26
Fit with the Atlas definition
Programme / growth zone · not a facility
Primary AI purpose
AI Growth Zone with a separate SUNRISE subproject.
Specialised processors
The zone itself is not a processor installation.
Supporting engineering
Subproject engineering must be assessed separately from the wider designation.
One named supercomputer and the wider commercial zone are separate developments. The 2026 opening targets varied by source; commissioning was not verified.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
Trawsfynydd AI Growth Zone siteProgramme / growth zone · not a facilityIn discussions · Project evidence 2026-11-26
Fit with the Atlas definition
Programme / growth zone · not a facility
Primary AI purpose
Named AI Growth Zone location.
Specialised processors
No installed AI processor inventory verified.
Supporting engineering
Designation is not a complete facility specification.
The site remains a designated zone anchor. The council decision relates to a skills and business facility. It does not establish a commissioned data centre.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
South Wales AI Growth ZoneProgramme / growth zone · not a facilityProposed · Project evidence 2026-11-26
Fit with the Atlas definition
Programme / growth zone · not a facility
Primary AI purpose
Multi-site AI Growth Zone.
Specialised processors
No single inventory corresponds to this marker.
Supporting engineering
Participating facilities have their own power/cooling and delivery stages.
Vantage and Nebius announced an agreement based at the existing Newport campus. The wider zone’s projected capacity is a regional ambition.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
Stargate UK / Cobalt Park proposalProgramme / growth zone · not a facilityPaused · Project evidence 2026-11-26
Fit with the Atlas definition
Programme / growth zone · not a facility
Primary AI purpose
Multi-site sovereign AI programme, with paused OpenAI commitment.
Specialised processors
Explored GPU offtake is not evidence of equipment installed at this marker.
Supporting engineering
No single programme-wide facility specification can establish local operation.
Paused programme; existing Cobalt Park buildings are not all paused or proven AI.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
Isambard-AIEvidenced AI operationOperational · Project evidence 2026-11-26
Fit with the Atlas definition
Evidenced AI operation
Primary AI purpose
University-operated national AI Research Resource; AI training purpose documented.
Specialised processors
5,448 NVIDIA GH200 superchips across phases1/2.
Supporting engineering
Purpose-built5MW system, direct liquid cooling and Slingshot network documented.
Evidenced operating AI installation; not a certification of every engineering component.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
Dawn AI supercomputerEvidenced AI operationOperational · Project evidence 2026-11-26
Fit with the Atlas definition
Evidenced AI operation
Primary AI purpose
Cambridge provides Dawn as national AI Research Resource compute.
Specialised processors
1,024 Intel Max1550 GPUs.
Supporting engineering
Dell/Intel system, direct liquid cooling and high-performance interconnect documented.
Evidenced operating AI installation inside a host data centre; not the whole building.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
Ada Docklands campusMixed / broader infrastructure · AI predominance unverifiedUnder construction · Project evidence 2026-11-26
Fit with the Atlas definition
Mixed / broader infrastructure · AI predominance unverified
Primary AI purpose
Operator expressly supports any combination of cloud, AI and general high-density workloads.
Specialised processors
No specific installed AI inventory verified.
Supporting engineering
Flexible high-density power and air/liquid cooling document AI readiness.
Ada’s dated 26 February announcement targets mid-2028 for the first 70 MW building. The current project page also carries an undated 2027 statement. The first building and full 210 MW campus have different scales.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
AI proposal / commitment · technical evidence incomplete
Primary AI purpose
Nebius agreement identifies an AI deployment within a broader existing campus.
Specialised processors
High-density NVIDIA infrastructure is announced; installed deployment not reverified.
Supporting engineering
AI training/inference capacity commitment; technical and operational scope is deployment-specific.
148 MW is the campus design figure for critical IT load. The operator has not confirmed commissioning of the separate Nebius installation.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
Mixed / broader infrastructure · AI predominance unverified
Primary AI purpose
Recorded operator material describes a high-performance campus.
Specialised processors
No site-specific installed AI inventory verified.
Supporting engineering
Campus planning / power envelope does not establish an equipped AI system.
Retained as AI-ready / mixed infrastructure context, not confirmed AI.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
Google North WealdAI scope unverifiedApproved · Project evidence 2026-11-26
Fit with the Atlas definition
AI scope unverified
Primary AI purpose
General data-centre planning evidence; primary AI purpose unresolved.
Specialised processors
No site-specific processor deployment verified.
Supporting engineering
Outline consent covers up to two buildings. Dedicated AI engineering and installed hardware remain unverified.
A separate July 2026 parish notice concerned housing. Construction and installed AI processors remain unverified.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
AI proposal / commitment · technical evidence incomplete
Primary AI purpose
Developer proposes hyperscale/AI infrastructure.
Specialised processors
No site-specific installed AI hardware verified.
Supporting engineering
Consultation-stage campus; required complete AI engineering not established here.
Council records 0625/PAC/25 as pre-application. The 250 MW demand capacity is separate from the battery storage consenting route. A newer planning decision could not be confirmed.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
AI proposal / commitment · technical evidence incomplete
Primary AI purpose
Developer proposes hyperscale/AI infrastructure.
Specialised processors
No site-specific installed AI hardware verified.
Supporting engineering
Campus sustainability/power proposals do not settle an AI system design.
Not an equipped AI facility.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
AI proposal / commitment · technical evidence incomplete
Primary AI purpose
Original AI-campus proposal is no longer being progressed.
Specialised processors
No installed AI inventory verified.
Supporting engineering
Proposal was not a commissioned installation.
Paused/withdrawn proposal retained for history only.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
Thames Valley Park data-centre proposalAI scope unverifiedProposed · Project evidence 2026-10-12
Fit with the Atlas definition
AI scope unverified
Primary AI purpose
Recorded proposal is a data centre; primary AI workload not established.
Specialised processors
No specific AI equipment/customer verified.
Supporting engineering
72MW IT and fuel-cell proposals describe infrastructure rather than an AI cluster.
The promoter describes 72 MW IT load. Wokingham’s current determination was unverified during the November review.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
AI proposal / commitment · technical evidence incomplete
Primary AI purpose
Council/developer material identifies dedicated AI intent.
Specialised processors
No equipped accelerator inventory verified.
Supporting engineering
Permission and campus capacity are not full AI-system verification.
The direct planning register was inaccessible. A later reserved-matters decision, construction milestone or deployed hardware was not verified.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
Recorded screening/press evidence describes a data-centre campus.
Specialised processors
No specific equipped AI deployment verified.
Supporting engineering
Campus/BESS proposals; primary AI system design unresolved.
The council issued a screening opinion in 2025. The November review could not verify a subsequent data-centre application or decision. A separate battery case does not establish the data-centre stage.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
Mixed / broader infrastructure · AI predominance unverified
Primary AI purpose
Recorded campus is designed for data-centre/high-density demand.
Specialised processors
No selected AI installation verified.
Supporting engineering
IT power and phased construction evidence; predominant AI use not demonstrated.
A Section 35 direction and consultation do not confer planning approval. The first-centre and later-building dates are indicative.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
Quest Park Data CampusMixed / broader infrastructure · AI predominance unverifiedProposed · Project evidence 2026-11-26
Fit with the Atlas definition
Mixed / broader infrastructure · AI predominance unverified
Primary AI purpose
Data-centre campus proposals; primary AI use not verified.
Specialised processors
No site-specific AI processor inventory verified.
Supporting engineering
Grid/private-wire proposals support supply strategy, not installed AI compute.
The 2034 date is for a grid connection. Earlier permission for film studios is separate. No opening date or data-centre consent verified.
Scope assessment 12 November 2026. Documentary assessment of cited public evidence; no site inspection. Existing project/source verification dates are retained.
AI proposal / commitment · technical evidence incomplete
Primary AI purpose
The operator targets 2028 ready-for-service. Reserved matters approval covers a first building at Foyle Port.
Specialised processors
Installed AI processors not verified for this project.
Supporting engineering
Operator describes high-density readiness. No commissioned processors disclosed.
The campus is intended for AI and cloud. Installed processors, tenant workloads and operating status remain unverified. Power figures refer to the campus.
Scope assessment 2026-11-26. Operator, institutional or planning evidence as linked.
Scope assessment is a review of published and recorded evidence, not a new commissioning inspection or a new planning-status check for every project. Existing project verification dates are retained. No minimum MW, fixed GPU count or mandatory cooling technology has been added to the agreed definition. Structural and other detailed engineering records are not always public; this is not an engineering certification.
CASE STUDY
How much does Loughton matter?
Loughton was meant to host 23,040 GPUs for Microsoft. Nscale says the power provider withdrew the scheduled connection and allocation, and the Microsoft agreement for the site ended.
23,040NVIDIA GB300 GPUs in the original plan50 → 90MWInitial AI capacity → scalable power allocation; not additiveUK share unknownNo like-for-like national compute denominator established
Why Loughton matters
The project shows how losing a power connection can derail a major AI deployment even after an anchor customer has signed. Nscale says it is exploring alternative power. The site remains delayed, with no verified replacement customer, power agreement or opening date.
39.3% of one original company package
Loughton’s GPU count divided by Nscale’s up-to-58,640 UK GPU announcement of 16 September 2025. This is a historical announcement-count comparison, not a share of UK compute, current stock, committed delivery or a performance measure.
LoughtonStargate potential
23,040 Loughton · original GB300 plan, customer withdrawn
31,000 Stargate ceiling · paused; initial 8,000 included
4,600 Separate GB300 announcement · delivery not reverified
The package mixes a first deployment with a possible later programme ceiling. Stargate’s GPU model was not specified in this announcement. No performance equivalence is assumed. The three components are counted once; the 58,640 headline is not added again.
Figures are dated individually. This register includes planned, contracted and installed capacity, with the basis shown on each row.
29 of 68 have a recorded MW figure; 5 of 68 have a GPU count or ceiling. Missing means undisclosed or unverified, not zero. These coverage counts describe the register.
68 entries shown
Capacity units and phases are kept separate. Select a project for its current recorded status, council and sources. No national total is calculated.
Project / stage
Power scale / basis
GPUs / model
Phase and timing / evidence
Mixed / broader infrastructure · AI predominance unverifiedOperational
Not disclosedNo MW verified in recorded sources
Not disclosedCount and model not recorded
See recorded capacity; no conversion from investment, acreage or GPU count to MWCapacity record checked 2026-10-12Capacity evidence ↗
Mixed / broader infrastructure · AI predominance unverifiedUnder construction
720MWIT load
Not disclosedCount and model not recorded
Full campus; 72MW per building; five phases to 2035Capacity record checked 2026-10-19Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteUnder construction
Not disclosedNo MW verified in recorded sources
Not disclosedCount and model not recorded
See recorded capacity; no conversion from investment, acreage or GPU count to MWCapacity record checked 2026-10-12Capacity evidence ↗
Documented AI design · live service unverifiedUnder construction
17.6MWBuilding capacity
Not disclosedCount and model not recorded
KLON-03 only; original 2026 ready-for-service target, not verified achievedCapacity record checked 2026-10-19Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteApproved
Not disclosedNo MW verified in recorded sources
Not disclosedCount and model not recorded
The 2027 first-phase target and peak campus ambition are operator plans. The decision has limited scope. The Chesterfield operation is separate.Capacity record checked 2026-11-26Capacity evidence ↗
Documented AI design · live service unverifiedDelayed · Microsoft withdrawn
50MWAI / HPC capacity
23,040NVIDIA GB300Original first deployment; customer withdrawn; original Q1 2027 target challenged
Original deployment plan, with power allocation scalable to 90 MW. The scheduled connection and associated allocation for the Microsoft agreement were withdrawn.Capacity record checked 2026-11-26Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteProposed
1,000MWIT load (recorded proposal)
Not disclosedCount and model not recorded
Upper full-campus proposal; first phase targeted 2029, full buildout undatedCapacity record checked 2026-10-12Capacity evidence ↗
AI scope unverifiedApproved
Not disclosedNo MW verified in recorded sources
Not disclosedCount and model not recorded
See recorded capacity; no conversion from investment, acreage or GPU count to MWCapacity record checked 2026-10-12Capacity evidence ↗
Programme / growth zone · not a facilityProposed
1.4MWSubproject facility power
Not disclosedCount and model not recorded
SUNRISE only; wider zone not quantified; June 2026 target not verified achievedCapacity record checked 2026-10-12Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteApproved
Not disclosedNo MW verified in recorded sources
Not disclosedCount and model not recorded
See recorded capacity; no conversion from investment, acreage or GPU count to MWCapacity record checked 2026-10-12Capacity evidence ↗
Programme / growth zone · not a facilityIn discussions
Not disclosedNo MW verified in recorded sources
Not disclosedCount and model not recorded
See recorded capacity; no conversion from investment, acreage or GPU count to MWCapacity record checked 2026-10-12Capacity evidence ↗
Programme / growth zone · not a facilityProposed
1,000MWProgramme potential (over)
Not disclosedCount and model not recorded
Regional ambition early 2030s; overlaps participating facilities; not additiveCapacity record checked 2026-10-12Capacity evidence ↗
Programme / growth zone · not a facilityPaused
Not disclosedNo MW verified in recorded sources
31,000NVIDIA, model not specifiedPotential later ceiling; initial exploration up to 8,000 is included, not additional; programme paused
See recorded capacity; no conversion from investment, acreage or GPU count to MWCapacity record checked 2026-10-12Capacity evidence ↗
Evidenced AI operationOperational
5MWFacility power
5,448NVIDIA GH200Operating phases 1 and 2; corrected earlier 5,444 transcription
Operating research facility; phases 1 and 2Capacity record checked 2026-10-19Capacity evidence ↗
Evidenced AI operationOperational
Not disclosedNo MW verified in recorded sources
1,024Intel Max 1550Operating Dawn installation
See recorded capacity; no conversion from investment, acreage or GPU count to MWCapacity record checked 2026-10-19Capacity evidence ↗
Mixed / broader infrastructure · AI predominance unverifiedUnder construction
210MWCampus capacity
Not disclosedCount and model not recorded
Three 70MW buildings; first building mid-2028; later dates unspecifiedCapacity record checked 2026-10-19Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteOperational
148MWCritical IT load at full campus build-out
Not disclosedCount and model not recorded
Operator design figure. The live dedicated AI capacity across the campus was not disclosed.Capacity record checked 2026-11-26Capacity evidence ↗
Mixed / broader infrastructure · AI predominance unverifiedApproved
Not disclosedNo MW verified in recorded sources
Not disclosedCount and model not recorded
See recorded capacity; no conversion from investment, acreage or GPU count to MWCapacity record checked 2026-10-12Capacity evidence ↗
AI scope unverifiedApproved
Not disclosedNo MW verified in recorded sources
Not disclosedCount and model not recorded
See recorded capacity; no conversion from investment, acreage or GPU count to MWCapacity record checked 2026-10-12Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteProposed
1,000MWCampus potential (up to)
Not disclosedCount and model not recorded
Conditional phased construction programme 2027–2035; first operation undatedCapacity record checked 2026-10-12Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteProposed
300MWCampus power (basis unspecified)
Not disclosedCount and model not recorded
Proposed campus; operation target 2028; not energised capacityCapacity record checked 2026-10-12Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteProposed
550MWCampus power (basis unspecified)
Not disclosedCount and model not recorded
Proposed campus; 2030 grid milestone is not openingCapacity record checked 2026-10-12Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteProposed
250MWCampus power (basis unspecified)
Not disclosedCount and model not recorded
Proposed campus; opening undatedCapacity record checked 2026-10-12Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteProposed
200MWCampus power (basis unspecified)
Not disclosedCount and model not recorded
Proposed campus; opening undatedCapacity record checked 2026-10-12Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteProposed
300MWCampus power (basis unspecified)
Not disclosedCount and model not recorded
Proposed campus; opening undatedCapacity record checked 2026-10-12Capacity evidence ↗
AI proposal / commitment · technical evidence incompletePaused
Not disclosedNo MW verified in recorded sources
Not disclosedCount and model not recorded
See recorded capacity; no conversion from investment, acreage or GPU count to MWCapacity record checked 2026-10-12Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteProposed
100MWFirst-phase compute capacity (up to)
Not disclosedCount and model not recorded
The first-phase target is conditional. Up to 500 MW is a later development ambition; first-phase and later figures are not added.Capacity record checked 2026-11-26Capacity evidence ↗
AI scope unverifiedProposed
72MWIT load
Not disclosedCount and model not recorded
Proposed facility; opening undatedCapacity record checked 2026-10-19Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteApproved
Not disclosedNo MW verified in recorded sources
Not disclosedCount and model not recorded
See recorded capacity; no conversion from investment, acreage or GPU count to MWCapacity record checked 2026-10-12Capacity evidence ↗
AI scope unverifiedProposed
300MWCampus power (basis unspecified)
Not disclosedCount and model not recorded
Proposed campus; approximate 2030 research date, not developer commitment; battery excludedCapacity record checked 2026-10-12Capacity evidence ↗
Mixed / broader infrastructure · AI predominance unverifiedProposed
300MWIT load (recorded proposal)
Not disclosedCount and model not recorded
Whole proposed campus; first centre around 2031, third earliest 2035Capacity record checked 2026-10-12Capacity evidence ↗
Mixed / broader infrastructure · AI predominance unverifiedProposed
720MWProposed full-campus IT load
Not disclosedCount and model not recorded
Up to 720 MW IT across four buildings. Proposed total site electrical demand up to 1 GW. Grid connection is a separate milestone.Capacity record checked 2026-11-26Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteProposed
1,500MWAI compute capacity (up to)
Not disclosedCount and model not recorded
Full proposal; no opening date; separate 1.8GW battery excludedCapacity record checked 2026-10-12Capacity evidence ↗
Evidenced AI operationOperational
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
Host-wide power and detailed cooling specifications are undisclosed for this installation.Capacity record checked 2026-11-26Capacity evidence ↗
Evidenced AI operationOperational
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
Global Switch’s campus power is separate from CoreWeave’s allocation.Capacity record checked 2026-11-26Capacity evidence ↗
The 4,000 figure is the announced initial scope. The launch does not independently inventory installed accelerators.Capacity record checked 2026-11-26Capacity evidence ↗
Evidenced AI operationOperational
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
The system’s name reflects its research role. It shares the Kao Harlow campus with other separately tracked deployments.Capacity record checked 2026-11-26Capacity evidence ↗
Evidenced AI operationOperational
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
The count describes compute nodes. It does not describe the GPU count or every Hartree workload.Capacity record checked 2026-11-26Capacity evidence ↗
Evidenced AI operationOperational
5MW5 MW of direct liquid-cooled capacity
Not disclosedCount and model not recorded
Operator-stated capacity. The planned Era4 project in Newport is a separate development.Capacity record checked 2026-11-26Capacity evidence ↗
Evidenced AI operationOperational
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
This entry covers the dedicated AI installations. The facility also hosts broader high-performance computing.Capacity record checked 2026-11-26Capacity evidence ↗
Evidenced AI operationOperational
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
The marker indicates Cambridge. Exact building and separation from Dawn are unverified, so there is no separate site claim.Capacity record checked 2026-11-26Capacity evidence ↗
Evidenced AI operationOperational
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
Separate installation on the Harlow campus. Later GB200 rollout was announced separately.Capacity record checked 2026-11-26Capacity evidence ↗
Evidenced AI operationOperational
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
HX3 is separate from Imperial’s general HX2 service and the host’s wider customer estate.Capacity record checked 2026-11-26Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteApproved
The campus is intended for AI and cloud. Installed processors, tenant workloads and operating status remain unverified. Power figures refer to the campus.Capacity record checked 2026-11-26Capacity evidence ↗
Mixed / broader infrastructure · AI predominance unverifiedOperational
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
The evidence supports mixed research computing. The proportion dedicated to AI is unknown.Capacity record checked 2026-11-26Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteProposed
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
CWL1 operates as a broader campus. Installation commissioning and delivered AI capacity remain unverified.Capacity record checked 2026-11-26Capacity evidence ↗
Documented AI design · live service unverifiedCommissioning
1.4MW1.4 MW system; MI355X accelerators
Not disclosedCount and model not recorded
Benchmarking establishes an installed system. General user service was not verified. HPL is a benchmark of linear algebra performance.Capacity record checked 2026-11-26Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteUnder construction
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
DV1 is an existing site. The expansion remains separate from operating host capacity and the DV3 and DV4 projects.Capacity record checked 2026-11-26Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteProposed
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
An AI Growth Zone location gives policy context. Installed infrastructure and AI predominance remain unresolved.Capacity record checked 2026-11-26Capacity evidence ↗
Documented AI design · live service unverifiedProposed
22MW22 MW contracted across the campus
Not disclosedCount and model not recorded
The 22 MW is contracted scope. Its distribution across buildings and commissioning remain unverified.Capacity record checked 2026-11-26Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteProposed
14MW14 MW contracted at an existing campus
Not disclosedCount and model not recorded
The customer and installed tenant processors are undisclosed. The operating host and the AI deployment have separate stages.Capacity record checked 2026-11-26Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteApproved
33MW33 MW planned capacity
Not disclosedCount and model not recorded
Main construction and tenant commissioning remain unverified. Early works and remediation approvals are separate from building completion.Capacity record checked 2026-11-26Capacity evidence ↗
Mixed / broader infrastructure · AI predominance unverifiedUnder construction
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
Electrical infrastructure milestones do not establish live tenant AI compute.Capacity record checked 2026-11-26Capacity evidence ↗
Mixed / broader infrastructure · AI predominance unverifiedOperational
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
The share of capacity serving AI and installed tenant GPU scale are undisclosed.Capacity record checked 2026-11-26Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteApproved
5.6MW5.6 MW approved project
Not disclosedCount and model not recorded
Planning approval is a development milestone. AI workload mix and commissioning remain unresolved.Capacity record checked 2026-11-26Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteProposed
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
The planning submission and developer’s intended use do not establish an equipped installation.Capacity record checked 2026-11-26Capacity evidence ↗
AI scope unverifiedProposed
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
Screening is an early planning step. AI purpose and engineering remain unverified.Capacity record checked 2026-11-26Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteProposed
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
The primary AI purpose is developer-stated. Installed compute remains unverified.Capacity record checked 2026-11-26Capacity evidence ↗
Mixed / broader infrastructure · AI predominance unverifiedProposed
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
The room allocation is not delivered compute capacity. The service supports wider HPC and is distinct from the AIRR host competition.Capacity record checked 2026-11-26Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteProposed
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
Clusters are planned within the known campus. The announcement did not establish operating capacity.Capacity record checked 2026-11-26Capacity evidence ↗
Mixed / broader infrastructure · AI predominance unverifiedApproved
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
Regional campus capacity and AI readiness do not establish installed AI compute here.Capacity record checked 2026-11-26Capacity evidence ↗
Mixed / broader infrastructure · AI predominance unverifiedApproved
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
The wider Vantage regional plan is separate. No commissioned AI installation is established at this site.Capacity record checked 2026-11-26Capacity evidence ↗
Mixed / broader infrastructure · AI predominance unverifiedProposed
Not disclosedNo comparable MW figure verified
Not disclosedCount and model not recorded
This is a separate proposal from Prosperity Parc. Final design and consent remain unresolved.Capacity record checked 2026-11-26Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteProposed
Not disclosedNo verified MW figure
Not disclosedCount and model not recorded
The developer’s 2030 target is conditional. No consent, installed processors or anchor tenant are verified.Capacity record checked 2026-11-26Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteApproved
Not disclosedNo verified MW figure
Not disclosedCount and model not recorded
The approval and operator announcement do not establish installed hardware, construction start or an opening date.Capacity record checked 2026-11-26Capacity evidence ↗
AI proposal / commitment · technical evidence incompleteProposed
40MWProposed compute capacity
Not disclosedCount and model not recorded
40 MW is the facility proposal. The separate 200 MW announcement covers four sites.Capacity record checked 2026-11-26Capacity evidence ↗
AI scope unverifiedProposed
Not disclosedNo verified MW figure
Not disclosedCount and model not recorded
The application identifies a data centre. Published evidence has not established predominantly AI use or an opening target.Capacity record checked 2026-11-26Capacity evidence ↗
AI scope unverifiedProposed
Not disclosedNo verified MW figure
Not disclosedCount and model not recorded
This scheme is distinct from the earlier neighbouring 25/0138/FUL approval. Predominantly AI use and an opening target remain unverified.Capacity record checked 2026-11-26Capacity evidence ↗
How to compare these figures
IT load is equipment demand. Facility or grid power may include cooling and other overheads. “AI capacity” and campus-potential statements are not automatically equivalent to either. MW is a power measure, not GPU throughput. Different GPU models, interconnects, memory, workloads and utilisation prevent a simple chip-count-to-compute conversion.
Operating, approved and proposed capacity is not summed. A current operating campus can still quote its eventual full-buildout limit. First phases are not added to the campus that contains them. Growth zones and programmes can include separately mapped facilities. Batteries, investment spending and site area are excluded from compute totals. A valid national percentage would require a dated, deduplicated UK inventory with comparable hardware or a defined performance measure and common delivery horizon.
DELIVERY OUTLOOK · 50 ENTRIES
When could the pipeline arrive?
50 of 68 Explore entries. Explore also includes 16 operating and 2 paused entries. The timeline has 22 with dated evidence and 28 with timing unknown.
2026–2036. Marker size shows published power for facilities. Dashed markers have no comparable figure. Select a number or name for capacity, timing and sources.
Published / reported targetResearch estimateGrid dateChallenged original target
Scroll the timeline sideways to see later years.
DATE EVIDENCE
202620282030203220342036
Opening / service target15 entries · published or reported
Other dated evidence6 entries · milestone evidence
Customer withdrawn1 entry · original target challenged
Power figures can describe a phase, a campus or IT load. Open a project to see its basis. Later phases can repeat a number.
Timeline dates are milestones or targets. The full pipeline has no verified completion date.
SUPPLY CHAIN / INITIAL REVIEW DRAFT
Supply Chain View
Who supplies the UK data centre build-out, where domestic value can be created, and what we should investigate next.
Initial view · 13 October 2026 · Selected primary sources
Draft Atlas assessment — for discussion
Established core suppliers, with opportunities across specialist services
This is an international supply chain serving the UK. Our initial assessment is that design, installation, cooling integration, commissioning and continuing maintenance offer practical opportunities for UK businesses. This is a working hypothesis, not a market-share ranking or an investment recommendation.
The main layers and example players
Illustrative companies with documented services or projects. These examples are not an exhaustive supplier register, approved supplier list or evidence that they work on every Atlas project. “Active in the UK”, “UK manufacturing” and “British-owned” are different attributes.
Selected players and initial interpretations
Layer
Example players
Documented role
Draft interpretation
Design and engineering
Arup · Keysource
Site feasibility, technical design, energy efficiency and owner-side oversight.
UK manufacturing and installation can capture value even when ownership is international. Schneider’s Scarborough plant illustrates why ownership and local production should be tracked separately.
Cooling and thermal systems
Airedale by Modine · Vertiv
Chillers, precision cooling and associated thermal systems. Airedale also describes liquid-cooling and modular offerings.
Cooling integration and retrofits look promising as AI changes rack requirements. Whether a particular site needs liquid cooling depends on its actual equipment and design.
AI computing equipment
NVIDIA and its system partners
AI accelerators and systems. NVIDIA documents UK infrastructure partnerships including Nscale.
The accelerator layer has substantial international dependencies. Installing compute in Britain does not by itself establish British ownership of the technology or a domestic chip supply chain.
Who actually buys?
The developer, operator, main contractor and equipment manufacturer can each be a purchasing route. Mercury describes generators and transformers on many data centre projects as owner-furnished and contractor-installed: the owner selects and buys, while the contractor integrates them. Procurement arrangements vary by project.
Specialist electrical and mechanical packages, modular assembly, controls integration, commissioning, maintenance and efficiency upgrades. Existing suppliers may need additional delivery capacity; new entrants still need evidence of competence, quality and reliability.
Draft assessment
Where entry looks harder
Taking full responsibility for a large campus, supplying core accelerators, or replacing proven critical equipment vendors. Our hypothesis is that references, technical qualification, warranties and delivery capacity make entry harder here. This needs validation through actual procurement conversations.
Power determines when work becomes real
A September 2026 parliamentary answer reports 72.8GW of data centre capacity in the GB connection queue, based on 2025 data. Queued capacity is not a forecast of construction. Supplier opportunity should be assessed against funding, permissions and credible power delivery, not announcement totals alone.
Which contractors and equipment suppliers have confirmed appointments on the projects in the Atlas? Record public evidence, appointment dates and scope; leave unknowns explicit.
Measure the UK contribution
For each company, distinguish ownership, manufacturing location, UK workforce and local subcontracting. A UK office does not prove UK production; international ownership does not rule it out.
Understand access for smaller suppliers
Who holds the procurement package? What qualification, insurance, technical standards and reference projects are required? Which packages can be supplied locally?
Follow timing and missing layers
Add substations and transformers, backup generation, fibre, water systems, security and operations suppliers. Track procurement windows, long-lead equipment and commissioning capacity where evidence is available.
Proposed direction — open for review
Develop a supplier-to-project register: company → role → UK presence and ownership → confirmed project involvement → procurement route → evidence date. Keep sourced facts separate from opportunity assessments. No supplier market shares or contract allocations have been inferred.
How a project moves from an initial idea through planning, construction and commissioning, with different approval routes across the UK.
Researched 13 October 2026 · Primary sources linked throughout
From proposal to an operating data centre
A typical sequence, with parallel workstreams and different national consent systems. Projects can loop back, split into phases, stall or be refused; there is no automatic progression to operation.
1. Define the project and secure a viable site
The developer tests customer demand, land rights, finance, power, water and fibre. A growth-zone designation can support delivery but is not permission. Existing-building equipment upgrades may follow a different path from a new campus.
2. Discuss the proposal and select the consent route
Pre-application engagement helps identify the planning authority, likely impacts and required studies. Major schemes may require formal community consultation. Establish whether the decision will be local or national; a Section 35 direction selects England’s national route, not the outcome.
3. Prepare surveys, design and environmental evidence
Assess traffic, noise, landscape, ecology, flood risk, energy and water as relevant. EIA screening asks whether assessment is required; scoping identifies its coverage. Neither is approval. Scotland requires EIA for new data centres above 50MW; other assessment duties can still apply below that threshold.
The application must contain the required documents before assessment. The authority consults relevant bodies and provides opportunities for public comment. Pre-application representations and statutory application consultation are different stages.
5. Assess and decide — or enter appeal/call-in casework
For the local route, officers assess the proposal and the council decides under its committee/delegation arrangements unless ministers intervene. A national route involves examination and a ministerial decision. Refusal, appeal, withdrawal or redesign can interrupt the sequence.
6. Resolve the conditions and parallel requirements
Outline permission or Scottish permission in principle may leave details for later approval. Confirm which pre-start conditions must be met, and obtain applicable environmental permissions, building-control approvals and utility agreements. A battery, generation plant or grid connection can have a separate consent route.
Commercial commitments and utility delivery must align with the permitted design. Construction and phased approvals do not establish that the full campus is operational. Planning consent cannot guarantee a grid connection date.
Install and test computing, cooling, power and safety systems, then bring capacity into service. Continue complying with planning conditions and applicable environmental/security requirements. The Atlas calls a project operational only on supporting evidence, not because it has permission.
The Explore table now includes a sortable Council / planning authority column. Each project’s detail panel identifies the host authority, the known route, the evidence and remaining uncertainty. Authority identification is separate from an audit of every consent or condition. Regional zones and multi-site programmes may have several authorities.
05 / POLICY & STRATEGY
Who steers AI in the UK?
National AI leadership works alongside devolved governments, councils and separate regulatory bodies. Planning approval does not sit with the AI minister alone.
Researched 13 October 2026 · Primary sources linked throughout
KN
CURRENT AI MINISTER
Kanishka Narayan MP
Minister of State for Artificial Intelligence, jointly in the Cabinet Office and the Department for Business, Innovation, Science and Trade (BIST), appointed 20 July 2026. His former DSIT post ended on that date.
A functional overview of published portfolios. These connections do not imply that independent regulators report to the AI minister.
Prime Minister & CabinetPolitical direction and accountability
↓
Kanishka NarayanJoint AI minister · attends Cabinet
Cabinet OfficeStrategy, security and public services
PM’s AI TaskforceNarayan leads · Lord Vallance chairs
AI Security InstituteAdvanced-model risk research
AI Economics Institute + HM TreasuryEvidence on jobs and productivity
Public-sector adoptionGovernment use of AI
BISTCapability, infrastructure and industry
AI policy & Growth ZonesData infrastructure and site development
AI Research ResourceResearch compute access
Sovereign AIBacking domestic AI companies
Science, robotics & semiconductorsInnovation and wider adoption
Devolved governments and local planning authoritiesScottish Government · Welsh Government · Northern Ireland Executive departmentsCouncils and national park authorities: local plans, applications, community engagement and enforcement
Separate regulatory and parliamentary scrutinyCMA · FCA · ICO · Ofcom and other sector regulators · Parliament
Different bodies answer different questions: what to build, what to fund, what risks to test and which rules apply.
01
Political leadership and delivery
Kanishka Narayan leads the Prime Minister’s AI Taskforce and attends Cabinet. Lord Vallance chairs it, convenes government and industry expertise and reports directly to the Prime Minister. Its July launch placed the Taskforce in the Office for the Prime Minister and the Cabinet. The chair and minister have distinct roles; they are not interchangeable.
AISI evaluates advanced AI risks and supplies technical evidence. It is a research institute, not a regulator. Dr Jade Leung became Vice-Chair and Security Advisor to the AI Taskforce following a September transition from her full-time CTO and Prime Minister’s adviser roles. The announcement said a replacement PM adviser would be appointed in due course; no replacement is assumed here.
Chaired by Professor Simon Johnson, the Institute studies productivity, jobs, growth and how benefits are distributed. It incorporates the former Future of Work Unit. Its June launch described a joint Treasury–DSIT organisation; the current ministerial portfolio places it with the Cabinet Office and HM Treasury. It supplies evidence rather than setting policy.
The fund launched in April 2026 to invest in British AI companies and support access to compute, talent and procurement opportunities. James Wise is Chair; the current investment-team page lists Suzanne Ashman as Managing Partner. Funding backing of up to £500 million is a programme commitment, not evidence that the whole amount has been spent.
The AI Research Resource includes Bristol’s Isambard-AI and Cambridge’s Dawn. Public compute supports research and innovation alongside capacity used for security evaluations and companies supported through Sovereign AI. AI Growth Zones aim to enable large infrastructure projects; a designation alone does not confer planning permission or deliver electricity.
The Digital Regulation Cooperation Forum connects the CMA, FCA, ICO and Ofcom; each retains its own remit. Other sector regulators also matter. Parliamentary scrutiny remains separate from ministerial delivery: a September 2026 human-rights report called for stronger AI oversight. AISI testing should not be mistaken for a licence to deploy or a replacement for existing law.
These are distinct responsibilities, not a chain of command beneath the UK AI minister. National policy can promote an investment while a different authority decides whether it can be built.
England — councils and national planning ministers
Local planning authorities normally handle building proposals, using national and local planning policy. Depending on the location, a district, unitary or borough council has this role; county councils can have highways and other responsibilities. Some projects are directed into the national Development Consent Order route, where the relevant Secretary of State decides following examination. Host councils still contribute local evidence and can have post-consent responsibilities.
The Scottish Government has its own AI Strategy 2026–2031, alongside planning and environmental responsibilities. Councils normally determine applications; Scottish Ministers have call-in and appeal powers. The September 2026 direction requires EIA for new data centres exceeding 50MW; smaller schemes may still require assessment. Notification requirements also apply. Scottish development agencies and councils can support investment, while connected generation or storage may need separate energy consent.
Wales — Welsh policy, councils and national park authorities
AI Cymru sets Welsh priorities and describes cooperation with the UK on Growth Zones. Welsh local planning authorities assess applications under the Welsh system; these include councils and national park authorities. PEDW handles appeals and national casework where applicable, with ministerial decisions for relevant routes. For the Trawsfynydd anchor, distinguish Gwynedd’s council role from Eryri National Park Authority’s planning functions.
Northern Ireland — Executive departments and 11 councils
Planning responsibilities are shared between the councils and the Department for Infrastructure. Councils lead local development planning and most application decisions; the Department handles regionally significant and called-in applications. Northern Ireland also has its own economic and public-service institutions. The Atlas currently has no Northern Ireland project; that is a limit of the watchlist, not evidence of no development or no local role.
Councils can provide pre-application advice, assess impacts, consult residents and statutory bodies, decide local applications, impose and discharge conditions and undertake enforcement. Economic development teams may separately support investment. Town, parish and community councils can represent residents and comment, but usually do not determine the application. Promoting an investment and granting legal consent are different functions.
Selected primary-source overview of institutions, announced programmes and documented collaborations. Not an exhaustive inventory, benchmark ranking or investment-return forecast. The UK is one country; the EU comprises 27 member states plus shared institutions. Company claims describe their own products and ambitions, not independently verified model superiority.
Ministerial roles and programme plans can change. Historical source pages may retain their former department names; the current ministerial portfolio takes priority for the governance diagram.
06 / POLICY & STRATEGY
The UK and EU: rivals and partners
Competition for compute, capital and model capability coexists with shared research programmes and technical cooperation.
Researched 13 October 2026 · Primary sources linked throughout
THE KEY DISTINCTION
Where AI is built — and who controls it
Our assessment: the UK and EU compete for investment, talent and control of critical AI capabilities while continuing to share research and evaluation infrastructure. Neither hosting data centres nor attracting a foreign lab, on its own, secures domestic control of the full AI stack.
Atlas assessment based on the evidence below
Where they compete
Compare mechanisms and delivery status, rather than treating unlike funding totals as a scorecard.
Selected UK and EU approaches, checked 13 October 2026
AI Growth Zones combine support for power, planning and investment. The Compute Roadmap forecasts a need for at least 6GW of AI-capable data-centre capacity by 2030; this is a projected requirement, not installed capacity.
EuroHPC is implementing 19 AI factories and 13 antennas. Its July 2026 call seeks up to seven AI gigafactories in EU countries, with selection expected in early 2027 and operations within 18 months afterwards.
Competition concerns deployable power, chips, sites and skilled staff. An announced campus or procurement call is not an operating training cluster.
Sovereign AI backs UK companies with capital and practical support. The government’s April launch describes support extending beyond equity to compute, visas and procurement.
InvestAI’s headline €200 billion is an ambition to mobilise investment, including a €20 billion gigafactory facility. These are investment-mobilisation figures, not a single pot already spent by Brussels.
The UK fund and EU headline cover different activities, geographies and financing sources. Dividing one by the other would give a misleading league table.
Google DeepMind develops frontier systems within Google. The UK also backs homegrown developers such as Ineffable Intelligence, pursuing a different learning paradigm.
France’s Mistral supplies commercial language models and promotes open-weight AI. Its industrial links include a strategic partnership with Dutch chip-equipment maker ASML.
Research location, ownership, model availability and control over deployment are separate forms of advantage. “Made in Britain” does not automatically mean British-owned.
The UK has relied on existing sector regulators and laws, with continuing debate about cross-sector AI legislation. Its security institute provides research evidence.
The AI Act establishes a common risk-based framework and general-purpose-model obligations. Its implementation is phased, and the Commission’s current page reflects amended high-risk dates.
UK businesses serving the EU may also fall within the EU framework. This is a strategic overview; actual obligations depend on the model, use and market.
Does Britain have a Mistral equivalent?
The UK has significant model capability. A direct counterpart depends on whether you mean a commercial LLM vendor, domestic ownership or emerging frontier research.
Commercial language models
Mistral AI
France / EU
A European model developer with an open-weight strategy and commercial services. Open weights do not mean every model, licence or service is unrestricted. ASML’s September 2025 partnership illustrates industrial investment across EU borders.
The combined DeepMind–Google Brain lab develops systems including Gemini and AlphaFold. Google documents substantial UK AI work. This establishes frontier capability in the UK, while ownership and commercial control sit within Google rather than an independent British model company.
David Silver’s company is pursuing AI that learns through experience using reinforcement learning. Sovereign AI and the British Business Bank announced co-investment in April 2026. Its research ambition should not be presented as an already demonstrated, generally available Mistral-style LLM service.
The company’s services include image and audio generation; its terms identify an England-and-Wales entity for UK/EU customers. It is relevant to Britain’s model ecosystem, but generative media is a different product category from a general-purpose conversational LLM.
Documented channels range from shared compute to university innovation networks. Bilateral cooperation with France is labelled separately from EU-wide programmes.
1
Association in force
Horizon Europe — shared research funding
The UK’s association was finalised in December 2023, enabling participation in the research programme from 2024 subject to programme rules. This provides a route for joint AI research; it is not EU membership or automatic eligibility for every digital funding scheme.
UK organisations can join eligible Horizon-funded EuroHPC work. The UK Compute Roadmap explicitly points to European supercomputers and AI factories as part of international access. Eligibility varies by call; membership should not be read as an entitlement to host an EU-funded gigafactory in Britain.
Cambridge’s ai@cam became one of eight inaugural ELIAS innovation nodes, linking research, entrepreneurship and European partners. This is a practical example of AI collaboration beyond data centres, focused on turning scientific work into applications and companies.
The industrial-strategy partnership includes supporting AI adoption in small and medium-sized businesses. It is cooperation with an EU member state, rather than an EU-wide joint frontier-model programme. The statement describes intended cooperation; it does not document a completed joint LLM.
The UK, European Commission and France participated in the international safety-institute network’s first meeting in November 2024. The channel supports technical dialogue on advanced-model risks. It is distinct from merging regulatory systems or jointly owning a model.
Selected primary-source overview of institutions, announced programmes and documented collaborations. Not an exhaustive inventory, benchmark ranking or investment-return forecast. The UK is one country; the EU comprises 27 member states plus shared institutions. Company claims describe their own products and ambitions, not independently verified model superiority.
Ministerial roles and programme plans can change. Historical source pages may retain their former department names; the current ministerial portfolio takes priority for the governance diagram.